5
13
Advantage

注:表格可左右滑动

Contrast / Type

Aluminum Alloy Formwork

Steel Formwork

Traditional Wooden Formwork

Load Performance (KN/㎡)

60

30

30

Use Times

More than 200 times

30-40

6

Construction Period (day/layer)

3-5 

5-7

5-7

Construction Efficiency

30-40㎡/day per person

15-20㎡/day per person

10-15㎡/day per person

Engineering Quality

Flatness and smoothness meet the requirements on finish and decoration

The surface is rough, the precision is not high, and the later manual processing is required. The cost is 18 yuan/㎡

The surface is rough, the precision is not high, and the later manual processing is required. The cost is 18 yuan/㎡

Recovery Benefit

30% high residual value

15% high residual value

0

Sales price (yuan/㎡) including all accessories

1100-1200

500

150

Lease (30 floors)

22~25 yuan/㎡ (reference)

RMB7/㎡

Only sell not rent

Staff Training

3 months

5 months

More than two years

Installation machinery fee (yuan/㎡)

0

5

1



Contrast / Type

Aluminum Alloy Formwork

Traditional Wooden Formwork

Construction Area

The building area is 500㎡, and the developed area is 1750㎡

Material Price

About 1100-1200 yuan/㎡, including a set of formwork + 3 sets of supports + 1 floor of accessories

150 yuan/㎡ (wood formwork + wood beam + support + iron nail) including one set of formwork + 3 sets of support

Use Times

More than 200 times

5 times

Whether to support the amount of early dismantling formwork

Must include early disassembly formwork support technology, one set of formwork, one set of accessories, three sets of support

Generally do not include early disassembly formwork support technology
One set of formwork, one set of support

Material Spec.

Formwork thickness 4mm, side thickness 6-8mm, side height 65mm Support: high-strength Q235 steel pipe support

15mm thick laminated plywood support: Q235 steel pipe fastener scaffolding

Recovery Value

30%

0% (cleaning fee is charged for abandoned formwork)

Decoration Fee

The concrete surface is smooth and clean. The door and window openings, balcony bay window plates, stairs, wall column beam surfaces and nodes are formed at one time, with minimal repairs, which can greatly save the cost of project decoration and plastering.

The amount of concrete surface repairs is increasing, construction waste disposal costs, and environmental cleanup safety issues.